Completed -
The system is running stable for over an hour. The maintenance window is therefore officially closed.
Mar 17, 23:10 CET
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Mar 17, 20:00 CET
Scheduled -
We are undergoing a migration of our systems to a new datacenter. The planned timeline is as follows:
- Before 8p.m.: All systems are fully operational and have been tested in the new datacenter.
- 8:00 p.m.: DNS records will be updated to point to the new datacenter’s IP addresses.
- 10:00 p.m.: Following a two-hour waiting period to ensure DNS caches are refreshed, the old datacenter will be decommissioned.
- After 10:00 p.m.: Post-migration tasks will be executed.
No disruptions are expected for our customers during the migration. This maintenance window is solely a precaution to address the very unlikely event of unexpected downtime.
We will keep you updated on the status of the migration.
Mar 17, 16:35 CET